You ask in plain words
With whatever notes or documents you already have.
If our systems went down, would we be back up within our recovery targets?
Which recovery targets will be missed?
Your notes
Separate crews; all times hours after outage. NET takes 2, target 3, no prerequisite. DATA takes 5, target 6, none. DESK takes 2 after NET and DATA, target 6. ORDERS takes 3 after DESK, target 8.
Your agent answers with a checked method
It runs 5 checks before it replies.
Your agentUsing this skill
NET and DATA can finish at hours 2 and 5. DESK waits for both, then needs two hours, so it finishes at hour 7 against a six-hour target. ORDERS follows at hour 10 against an eight-hour target. Test the DATA to DESK to ORDERS sequence in the next exercise.
- An objective is a desired service outcome; it does not shorten an upstream restart.
- Adding all parallel prerequisites overstates the critical path. Ignoring a serial prerequisite understates it.
- Counting a fallback that relies on an unavailable person, a lost key or an expired credential as a working route.
- Leaving out suppliers' own restore times, such as an internet or software provider's, makes the plan look faster than it is.
- Presenting an untested estimate as a proven recovery time.
Why that’s right. The desk waits for the slower prerequisite. Order entry then inherits the delay.
Is it the right skill?
What it’s for, and when another skill or a person is the better choice.
Use it when
- A small business wants to know whether its continuity plan meets its recovery targets.
- A runbook lists restart steps and someone asks which services will be late and why.
- Before a recovery exercise, the team wants to find the longest dependency chain to test.
Not the right skill when
- Writing a full business continuity plan or preparing for ISO 22301 certification.
- Running a live cyber incident. Follow the incident response plan and get specialist help.
- Setting the recovery targets themselves. Those come from a business impact analysis agreed with the service owners.
The method it follows
7 steps, in order, every time.
- Fix the scenario and the clock: hour zero is the interruption, and every target and duration is in hours on that clock. Where a maximum tolerable period of disruption is given, check the recovery time objective is shorter.
- Map prerequisites: systems, people, suppliers, premises, credentials and data restores. Distinguish mandatory dependencies from documented alternative routes. A route with unavailable staff, expired credentials or inaccessible recovery material cannot support a promised finish. Flag missing or circular dependencies before scheduling.
- Apply the stated resource model. Independent tasks may run together; if staff or equipment are shared, ask for a priority and capacity assumption rather than assuming parallel work.
- Schedule each task to start when its last prerequisite is ready and finish after its own restart duration. Where alternatives exist, use the earliest route whose prerequisites and timing are evidenced. A service that depends on an unresolved service is unresolved too.
- Compare each finish with its recovery objective on the same clock and report how late each service is. A stated target does not supply missing capacity.
- Trace the critical path to each late service: the chain of prerequisites that sets its finish time. That is the chain to shorten or test first.
- Label each duration as tested or estimated, and propose evidence for the longest blocking dependency in the next exercise.
What to have ready
If something’s missing, your agent asks before it starts.
- Service IDs, recovery time objectives and estimated restart durations
- Prerequisite map, shared resource constraints and starting assumptions

What disruption are you planning for, and when does the clock start?

For each service, what is its recovery target and what must be working before it can restart: systems, people, suppliers, data?

Can recovery tasks run at the same time, or do they share the same people or equipment?

Which restart times come from a real test or incident, and which are estimates?
Try it on your own AI
A new question with a known answer, so you can check your AI gets it right.
-
Copy the questionCan the recovery sequence finish as written? Return only JSON following the skill’s test format. Independent crews. PAY takes 1 hour after LEDGER, target 4. LEDGER takes 2 hours after PAY, target 5. STATUS takes 1 hour independently, target 1.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
No task in the circular pair can start, but the independent status service can.
{
"finish_hours": {
"PAY": null,
"LEDGER": null,
"STATUS": 1
},
"late_hours": {},
"unresolved": [
"LEDGER",
"PAY"
]
}
The check runs in your browser. Nothing you paste is sent anywhere.
-
Copy the questionCan payroll be recovered by its four-hour target? Return only JSON following the skill’s test format. PAY takes 1 hour after any one of three routes: KEY was lost, ADMIN is unavailable throughout the planning horizon, ENVELOPE contains an expired credential. These are failed recovery options, not services to be timed. No other route or restoration time is documented.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
No usable route reaches payroll. The four-hour objective cannot establish a finish time.
{
"finish_hours": {
"PAY": null
},
"late_hours": {},
"unresolved": [
"PAY"
]
}
The check runs in your browser. Nothing you paste is sent anywhere.
Where the method comes from
Free to use and adapt with credit (CC BY 4.0).
Use this skill in Raq.com
Add it to your Skill Library and your agent applies it whenever a request matches. Edit it for your own business and keep every version.