description: "Check a tender or bid pack against the buyer's mandatory instructions, addenda and clarifications, and list what is missing, defective or unproven before the deadline. Use when someone asks whether their tender, ITT response or bid submission is complete, compliant or actually submitted."
license: CC-BY-4.0
metadata:
  author: Raq.com
  version: "2026-11-22"
  homepage: https://skills.raq.com/skills/check-tender-submission-completeness
---

# Check a tender for missing requirements

Map the buyer’s mandatory instructions to submitted evidence, including addenda, signatures and attachments.

## When to use this skill

- Someone is about to submit a tender, ITT, RFP or quotation response and wants to know whether anything mandatory is missing.
- The buyer has issued addenda or clarification answers that change word limits, forms, signatures, the deadline or the submission channel.
- A bid team wants to know whether a portal upload counts as a submitted tender.

## When not to use it

- Scoring the quality of the answers or predicting the evaluation result. Use the weighted bid scores skill to recalculate a published scoring matrix.
- Deciding whether a public buyer will accept a late or non-compliant tender. Under the Procurement Act 2023 that is the buyer's discretion, so raise it through the tender's clarification channel before the deadline.

## What you need

- Invitation to tender, schedules, amendments and clarification answers in issue order.
- Actual submission inventory, response text and current signed documents.

## Ask before you start

If any of these are missing or unclear, ask before doing the work.

- Can you share the full tender pack, including every addendum and the clarification log in issue order? A later addendum can change a limit, a form or the deadline.
- What exactly is in the submission as it stands: the files, the signed copies and the response text? A file list alone cannot show a signature or an answer.
- Has anything been submitted yet, and what does the portal show as its status or confirmation?
- Who is the buyer and which rules govern the procurement? The Procurement Act 2023 governs most public buyers in England, Wales and Northern Ireland for procurements started on or after 24 February 2025. Devolved Scottish authorities, earlier procurements and other countries follow their own rules.

## Method

1. Collect the governing documents for this opportunity and lot: tender notice, invitation to tender, schedules, every addendum and the clarification log, in issue order. Do not import requirements from a different competition, lot or jurisdiction.
2. Build a register keyed by the buyer's requirement IDs, with the wording, locator and version behind each row. Apply an addendum only to the requirements it explicitly changes and keep the remaining original instructions.
3. Separate mandatory deliverables, conditional requirements and scored preferences. Resolve each condition from supplied facts, such as a confirmed decision not to subcontract. If applicability is uncertain, hold it for clarification. Leave scored preferences out of the compliance check.
4. Inspect each submitted artefact: signature state, named template, completeness, currency and any word or page limit in the final instructions. A filename can establish presence but cannot prove a signature or a substantive answer.
5. Classify every mandatory requirement. Missing means no artefact, including one the narrative promises to send later. Defective means present but visibly failing, such as unsigned or over the limit. Review means the evidence cannot be inspected or is inconclusive. Not applicable needs a supporting fact.
6. Separate a pack that is ready from proof that the buyer received it. Use the latest official deadline, time zone and channel, and look for a portal submitted status or confirmation where the buyer requires one. An upload, a saved draft or an informal team email does not prove receipt. Under the Procurement Act 2023 a buyer may disregard a tender that breaches a procedural requirement in its tender documents, such as lateness or an exceeded word count.
7. For every open item, state what would clear it and who must act, then re-run the check after each fix.

## Checks before you deliver

- A promise in the narrative to attach a certificate does not establish that it is in the submission.
- A dated amendment takes precedence for its own clause. Do not import requirements from a different competition or jurisdiction.
- Checking against the original ITT after an addendum. A replaced word limit, form version or deadline can make a compliant pack non-compliant, or the reverse.
- Treating an upload as a submission. On the government eSourcing system a response stays in draft until Submit Response is confirmed, and buyers cannot see an unsubmitted response.
- Marking a conditional requirement not applicable without the fact that makes it so, such as a recorded decision not to use subcontractors.

## How to present the result

Start with a one-line verdict: ready to submit, or the number of mandatory items blocking submission. Then give a table with one row per mandatory requirement: ID, requirement as amended, evidence checked, status (met, missing, defective, needs review or not applicable) and the action that clears it. List scored items separately as outside the compliance check. End with the final deadline, the channel and the proof of receipt to keep.

## Worked example

**Request:** Check our pack against the final tender instructions.

**Supplied material:**

```text
ITT §2 M1 signed declaration; §3 M2 method max 400 words; §4 M3 attach insurance schedule; §5 M4 subcontractor form only if subcontracting. Optional brochure scores style. Addendum 2 replaces M2 limit with 500 words. Inventory: declaration unsigned; method 460 words; narrative says insurance will follow. No subcontractors.
```

**Answer:** Two mandatory items prevent submission. Sign the M1 declaration and attach the M3 insurance schedule. M2 meets the revised 500-word limit at 460 words. M4 does not apply because the bid uses no subcontractors.

## Structured output for tests

For an ordinary job, answer in the format above and point back to the supplied evidence. Use this structure only for the test cases published with this skill, or when someone asks for structured JSON.

Return ready (boolean), met, missing, defective, review and not_applicable as sorted arrays of mandatory requirement IDs. Exclude scored preferences. ready is true when missing, defective and review are all empty.

## Sources

- [Cabinet Office: Assessing competitive tenders (Procurement Act 2023 guidance)](https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/assessing-competitive-tenders-html): Current guidance under the Procurement Act 2023, updated August 2026. It requires any pass/fail criteria to be set out in the assessment methodology and gives a late tender and one over the prescribed word count as examples of breaching a procedural requirement, which lets the buyer disregard the tender.
- [Procurement Act 2023, section 19](https://www.legislation.gov.uk/ukpga/2023/54/section/19): Section 19(3) says a contracting authority must disregard a tender from a supplier that fails the conditions of participation and may disregard a tender that breaches a procedural requirement in the tender notice or associated documents. This is why the skill treats the deadline, channel and form instructions as mandatory.
- [Government Commercial Agency: eSourcing tool guidance for suppliers](https://www.gov.uk/government/publications/esourcing-tool-guidance-for-suppliers): The linked bidder guide (version 1.5, September 2026) says a response stays in draft until the bidder selects Submit Response and confirms, that an unsubmitted response is not accessible to buyers, and that submission sends an email alert and shows a banner. An upload alone is therefore not proof of receipt.

Test cases and an answer checker for this skill: https://skills.raq.com/skills/check-tender-submission-completeness