# Check weighted bid scores

Recalculate a published evaluation matrix and identify mandatory failures or missing scores before ranking suppliers.

## When to use this skill

- An evaluation panel or a bidder has a scoring matrix and wants the weighted totals and ranking recalculated.
- A relative price formula, such as lowest price divided by this price, may be using the wrong comparator.
- A bid failed a mandatory requirement or has a missing score, and someone wants to know how that affects the ranking.

## When not to use it

- Re-marking the quality answers or second-guessing an assessor's judgement. The skill checks the arithmetic and the published method, not the merits of each answer.
- Deciding whether a public award decision is lawful or can be challenged. That needs specialist procurement legal advice, and it should be sought quickly.

## What you need

- Buyer’s award methodology with weights, component maxima and mandatory criteria.
- Completed raw assessor scores and pass/fail decisions for each bid.

## Ask before you start

If any of these are missing or unclear, ask before doing the work.

- Can you share the published assessment methodology: criteria, maximum marks, weights, pass/fail gates, the price formula and any rounding or tie-break rule? The published method, not the spreadsheet, decides the result.
- Do you have the raw or moderated scores for every bid and every pass/fail decision? Weighted totals alone cannot be checked.
- Which rules govern the procurement? The Procurement Act 2023 governs most public buyers in England, Wales and Northern Ireland for procurements started on or after 24 February 2025. Devolved Scottish authorities, earlier procurements and other countries follow their own rules. Under the Act the buyer must assess against the methodology it published, so a different formula in the spreadsheet is itself a finding.

## Method

1. Write down the published method for each criterion: maximum raw score, weight, scoring formula and whether failing it disqualifies the bid. Under section 23 of the Procurement Act 2023 a public buyer covered by the Act must state the relative importance of its criteria and whether failure disqualifies, so work from that published version.
2. Confirm the weights total 100 and every raw score is within its range. If the weights do not total 100 or a maximum is missing, treat the methodology as invalid, mark every bid incomplete and ask. If criteria are only ranked in order of importance, a weighted total cannot be calculated; say so rather than inventing weights.
3. Apply disqualifying criteria first, and only those the methodology identifies as such. Exclude bids that fail and record why. Hold bids whose pass/fail decision is missing. A known mandatory failure takes precedence over an unscored component.
4. Treat a missing score as missing evidence and keep that bid out of the ranking as incomplete. A recorded zero is a valid score.
5. Calculate a proportional score as the raw score divided by its maximum, times the weight. For relative price, use exactly the published comparator set: for a lowest-eligible-price formula, settle every eligibility gate before choosing the reference price. An unresolved reference price makes every dependent score provisional.
6. Add the unrounded components. Use the published rounding stage, precision and tie-break. If none is published, compare unrounded totals, keep ties as ties and round half up to two decimals for display only.
7. Rank the eligible bids and name every bid tied for the top. Call it the arithmetic leader on this evidence, not the award, and list each difference from the buyer's own sheet.

## Checks before you deliver

- Five marks out of ten and five out of five contribute differently.
- An award criterion described as desirable cannot be promoted into a disqualifying condition by the assessor.
- Choosing the relative price benchmark before removing failed bids. A cheap disqualified bid sets an artificially low comparator and depresses every other price score.
- Rounding each component before adding them can create or break a tie. Round once, at the published stage.
- Treating a blank as zero. A missing score makes the bid incomplete; only a recorded zero counts as zero.

## How to present the result

Lead with the recalculated leader, or the reason no leader can be named yet. Then give a table with one row per bid: gate result, raw and weighted score for each criterion, total out of 100 and status (ranked, disqualified or incomplete). Below it, list each discrepancy from the buyer's own sheet with the criterion or cell, the figure used and the corrected figure.

## Worked example

**Request:** Cross-check the shortlist.

**Supplied material:**

```text
Proportional scoring: quality /5 weight 60, value /10 weight 40. Signed safety declaration is a mandatory pass. A 4,8 pass; B 5,10 fail; C 5,6 pass; D missing,10 pass.
```

**Answer:** C leads with 84/100: 60 quality points and 24 value points. A scores 80/100: 48 for quality and 32 for value. B failed the declaration gate. D has no quality score and cannot be ranked on this evidence.

## Structured output for tests

For an ordinary job, answer in the format above and point back to the supplied evidence. Use this structure only for the test cases published with this skill, or when someone asks for structured JSON.

Return scores as a map of eligible bid IDs to totals out of 100 rounded half up to two decimals, disqualified and incomplete as sorted ID arrays and leaders as a sorted array of tied highest eligible IDs. If the methodology or weights are invalid, put every bid in incomplete. A known mandatory failure takes precedence over an unscored component.

## Sources

- [Cabinet Office: Assessing competitive tenders (Procurement Act 2023 guidance)](https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/assessing-competitive-tenders-html): Current guidance, updated August 2026. Assessment must follow the published methodology, pass/fail criteria must be set out in it, and relative importance may be given as percentages, a ranking or another description. It also warns that relative price scoring derived from the lowest price can affect value for money and suggests scenario-testing.
- [Procurement Act 2023, section 23](https://www.legislation.gov.uk/ukpga/2023/54/section/23): Section 23(3) requires the buyer to describe the assessment methodology, to set out the relative importance of the criteria where there is more than one, and to say whether failing a criterion disqualifies a tender. These are the inputs the recalculation depends on.

Test cases and an answer checker for this skill: https://skills.raq.com/skills/check-weighted-bid-scores