name: find-contract-renewal-deadline
description: "Work out the last date to give notice under a contract's renewal or auto-renewal clause, using the notices clause, delivery method, deemed-receipt rules and the right holiday calendar. Use when someone asks when they must cancel, terminate or give notice before a contract rolls over."
license: CC-BY-4.0
metadata:
  author: Raq.com
  version: "2026-11-22"
  homepage: https://skills.raq.com/skills/find-contract-renewal-deadline
---

# Find a contract renewal notice deadline

Extract the current term, calculate when notice must arrive and tell the owner how to deliver it.

## When to use this skill

- A supplier contract, subscription or service agreement renews automatically unless notice is given.
- Someone asks for the last day to give notice, or whether a notice sent by email or at the weekend will count.
- A contract register needs renewal and notice dates diarised.

## When not to use it

- Deciding whether a renewal or notice clause is enforceable, or whether consumer law overrides it for a consumer subscription. Check the consumer rules for the person's country separately.
- Negotiating the renewal or drafting the substance of the notice. The skill finds the date, channel and evidence needed.

## What you need

- Signed agreement and effective variations, previous renewal history and term end.
- Notice clause, receipt rule, normal delivery channel and relevant holiday calendar if needed.

## Ask before you start

If any of these are missing or unclear, ask before doing the work.

- Can you share the signed contract and any variations, including the renewal clause and the separate notices clause? The delivery method and receipt rule are usually in the notices clause.
- When did the current term start or last renew, and what record shows it? Signature, service start and acceptance can be different dates.
- Where are the parties, and which public holiday calendar does the contract use? Bank holidays differ between England and Wales, Scotland and Northern Ireland, and between countries.

## Method

1. Locate the operative renewal clause and the separate notices clause, including amendments. Record the clause numbers.
2. Establish the anchor date: the current term end or renewal date from signed evidence and any recorded exercise of an option. If the term runs from an event such as service acceptance, find the record of that event; do not substitute the signature date.
3. Count with the contract's own unit. Subtract calendar days from the stated date for a received-by rule. For whole calendar months, use the corresponding date and check the contract's end-of-month treatment. Business-day rules need the stated calendar.
4. Read whether the deadline governs dispatch, receipt or deemed receipt. Work backwards through any delivery cut-off time, time zone, weekend and holiday rules to the last effective delivery opportunity, and report the nominal date separately if it differs. If the holiday calendar is essential but missing, give the last possible time subject to that calendar and leave the confirmed deadline unresolved.
5. Do not move a deadline that falls on a weekend or holiday unless the contract says so. Without a business-day or deemed-receipt rule the nominal date stands; suggest sending earlier as a practical margin, but report the contractual date.
6. Record the evidence locator, required channel and notice trigger. When the anchor or counting convention cannot be established, keep the supported facts and return an unresolved date. This is a diary aid, not a decision about enforceability.
7. Suggest a reminder well before the deadline, leaving time to decide, get approval and send, and say what proof of delivery to keep.

## Checks before you deliver

- Auto-renewal length is different from the notice period.
- A draft email, an invoice contact and a notice delivered to the specified address are different pieces of evidence.
- Counting from the signature date when the term runs from service start or acceptance.
- Assuming a notice sent at the weekend counts that day. A deemed-receipt rule can move it to the next business day, after the deadline.
- Using a holiday calendar the contract does not name. UK bank holidays differ between England and Wales, Scotland and Northern Ireland.

## How to present the result

Lead with the date, and time if one applies, to diary and the channel to use, or with the missing fact that blocks a confirmed date. Then show the working: anchor date and its evidence, notice period, clause references, receipt rule and any weekend or holiday adjustment. Finish with a suggested reminder date and the proof of delivery to keep.

## Worked example

**Request:** What is the last permitted receipt date?

**Supplied material:**

```text
Order term ends 2027-03-31. Clause 6.2: rolls for another year unless notice is received at least 60 calendar days before term end. Clause 14: notice through customer portal. No adjustments or amendments.
```

**Answer:** Diary 30 January 2027 as the last date notice must reach the customer portal. The term ends 31 March and clause 6.2 requires 60 calendar days. Use the portal specified in clause 14 and retain its receipt.

## Structured output for tests

For an ordinary job, answer in the format above and point back to the supplied evidence. Use this structure only for the test cases published with this skill, or when someone asks for structured JSON.

Return deadline (ISO date or null), deadline_basis (receipt, dispatch or unknown), channel (email, post, portal, other or unknown), clause (operative identifier only, such as 6.2 or R4, the local clause marker may also be retained) and status (calculated or needs_information). For a deemed-receipt rule also give nominal_deadline and last_candidate, as YYYY-MM-DD HH:MM followed by the supplied time zone for a timed candidate. Use deadline for the confirmed last effective delivery date and needs_information when the calendar is essential but missing.

## Sources

- [GOV.UK: UK bank holidays](https://www.gov.uk/bank-holidays): GOV.UK lists separate bank holidays for England and Wales, Scotland and Northern Ireland, including substitute days. The skill asks which calendar the contract uses instead of assuming one.
- [Government Commercial Function: Contract management foundation guide](https://www.gov.uk/government/publications/civil-service-helping-you-with-managing-suppliers-and-contracts/contract-management-training-accreditation-foundation-level-takeaway-guide-html): The guide tells contract managers to start exit planning on larger contracts about 12 to 18 months before the contract ends and to review the plan at least annually. This is why the skill sets reminders well ahead of the notice date.

Test cases and an answer checker for this skill: https://skills.raq.com/skills/find-contract-renewal-deadline