description: "Rebuild a contract's agreed value and completion date from its change log, applying only approved and effective changes and holding unsigned, future or conflicting ones. Use when reviewing a change register, variation orders, change notices or contract amendments, or checking an invoice against them."
license: CC-BY-4.0
metadata:
  author: Raq.com
  version: "2026-11-22"
  homepage: https://skills.raq.com/skills/review-contract-change-log
---

# Review a contract change log

Rebuild the approved contract value and completion date while keeping requested variations separate.

## When to use this skill

- Someone needs the current agreed contract value or completion date after several variations or change notices.
- A change log mixes signed, unsigned, proposed and duplicate changes.
- An invoice needs checking against the charge agreed after changes.

## When not to use it

- Deciding whether a public contract modification is permitted under the Procurement Act 2023, or whether a contract change notice had to be published first. Refer that to the buyer's commercial or legal team.
- Negotiating or valuing a proposed change. The skill records what has been agreed, not what should be.

## What you need

- Baseline fee and completion date from the signed agreement.
- Change IDs, signatures, effective dates and signed fee/date adjustments.

## Ask before you start

If any of these are missing or unclear, ask before doing the work.

- What does the contract's change procedure require for a change to take effect, such as both signatures, a set form or an authorised signatory?
- At what date should the position be stated?
- Can you share every change notice in full, including duplicates, rather than a summary list? Copies and conflicting versions need comparing.

## Method

1. Start from the signed baseline: value, fee basis (a fixed sum or a rate per period), currency and completion date.
2. Use the change procedure's approval rule. Fix an as-of date and a unique ID for each notice. Treat an identical repeated copy as one notice, and hold conflicting signed versions for verification.
3. Sort notices by effective date and contractual sequence. A proposal, an unsigned request under a signed-change policy or a change effective after the as-of date cannot alter the current baseline.
4. Apply exactly what each approved change says: an incremental delta, a replacement amount or a recurring rate from an effective date. A replacement supersedes the named earlier amount; keep its history and stop the old rate when the replacement takes effect. If same-date changes conflict, use contractual precedence or hold the disputed amount instead of deciding by ID.
5. Record accepted zero-value time changes as well as fee changes. Reconcile the baseline plus approved changes to the new value and completion date, and show unresolved notices alongside.
6. When checking an invoice, apply the changes effective in its billing period and compare on the same fee and period basis. Report billed minus agreed as a signed amount.
7. For a public contract under the Procurement Act 2023 (most public buyers in England, Wales and Northern Ireland), flag any applied change that alters value or term without a recorded contract change notice, for the commercial lead to check. The Act generally requires the buyer to publish a notice before modifying a public contract unless an exemption applies.

## Checks before you deliver

- A requested service change can affect timing without adding money.
- Repeated attachments to email threads are often copies of one signed notice.
- Adding a replacement fee on top of the amount it replaces.
- Applying a change from its signature date when it states a later effective date.
- Counting a change signed by one party when the procedure requires both.

## How to present the result

Lead with the agreed value and completion date at the stated date. Then give a reconciliation table: the baseline, each applied change with its effect and effective date, and the new totals. List held changes separately with the reason and what would allow each to be applied. If an invoice was checked, give the agreed charge for its period and the difference.

## Worked example

**Request:** What is agreed as at 2026-07-31?

**Supplied material:**

```text
Baseline £10,000 and 2026-08-10. Both parties must sign. C1 both signed, effective July 2: +£800 and +5 calendar days. Identical C1 copy enclosed. C2 supplier signature only: +£300 and -3 days. C3 both signed, effective Aug 1: -£100.
```

**Answer:** At 31 July the agreed value is £10,800 and completion is 15 August 2026. C1 adds £800 and five days, and its duplicate counts once. C2 lacks the second signature. C3’s £100 reduction takes effect in August.

## Structured output for tests

For an ordinary job, answer in the format above and point back to the supplied evidence. Use this structure only for the test cases published with this skill, or when someone asks for structured JSON.

Return value and completion (ISO date), applied and held (sorted arrays of unique change IDs). Treat a conflicting duplicate as held, excluding every version from the provisional baseline. Currency is supplied by the contract. Keep value on the same fee and period basis as the baseline. For a requested check against an actual invoice include billed_less_agreed in that basis, after applying changes effective in its billing period.

## Sources

- [Government Commercial Function: Contract management foundation guide](https://www.gov.uk/government/publications/civil-service-helping-you-with-managing-suppliers-and-contracts/contract-management-training-accreditation-foundation-level-takeaway-guide-html): The guide says changes should be agreed through a contract change notice and recorded in the change control log, must be mutually agreed unless the contract says otherwise, and should still be formally recorded when they have no financial effect.
- [Cabinet Office: Guidance on contract modifications (Procurement Act 2023)](https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-manage-phase/guidance-contract-modifications-html): Updated July 2026. A public contract may be modified only on permitted grounds, a contract change notice must generally be published before the modification, and for contracts over £5 million the modification or modified contract must be published within 90 days. This is why the skill flags public-contract changes without a notice.

Test cases and an answer checker for this skill: https://skills.raq.com/skills/review-contract-change-log