You ask in plain words
With whatever notes or documents you already have.
What share of this supplier’s orders arrived on time and in full last month?
Calculate July OTIF as of 2026-07-31.
Your notes
A due Jul 4: 10 units; accepted 8 Jul 3, 2 Jul 5. B due Jul 10: 3 red, 2 blue; all accepted Jul 10. C due Jul 18: 5; 5 delivered Jul 17, one rejected. D due Aug 2. E due Jul 20 cancelled in full before dispatch.
Your agent answers with a checked method
It runs 5 checks before it replies.
Your agentUsing this skill
July OTIF is 1 of 3 orders, or 33.3%. B passed. A reached ten units a day late, and C had only four accepted by its due date. D is due in August and E was cancelled before dispatch.
- Counting shipment events rewards split deliveries and changes the denominator.
- A dispatch date cannot stand in for the date goods were accepted when the contract measures receipt.
- Include still-open overdue orders in a due-date cohort. A dispatch-only or completed-only export cannot establish performance for all orders due; request the order register or mark the denominator incomplete.
- Applying an unwritten grace period or excusing buyer-side delays without an agreed rule. Use only the definition in the contract.
- Quoting a percentage without its denominator. One order out of one and 400 out of 400 both read as 100%.
Why that’s right. A short acceptance and a late final quantity each fail the whole-order test.
Is it the right skill?
What it’s for, and when another skill or a person is the better choice.
Use it when
- A supplier review or contract KPI needs the percentage of orders delivered on time and in full.
- Deliveries arrive in several parts, some goods are rejected, or some orders are still overdue.
- Someone wants the list of orders that missed, to discuss with the supplier.
Not the right skill when
- Setting the KPI target or deciding a contract remedy for poor performance. Those come from the contract.
- Publishing a contract performance notice for a public contract. Under the Procurement Act 2023, which covers most public buyers in England, Wales and Northern Ireland, the buyer assesses KPIs on contracts over £5 million and publishes its rating; follow the buyer's KPI guidance for that step.
The method it follows
6 steps, in order, every time.
- Set the contract's measurement grain, cancellation policy and reporting period. Under the default whole-order convention, an order belongs to the period containing its last applicable promised line date and is pending until then, even if an earlier line has already missed. A line-level KPI uses a different denominator. Exclude fully cancelled orders under the stated default.
- Build the cohort from the order register, not the delivery log: every order whose last promised date falls in the period and on or before the cut-off, including overdue orders with nothing delivered.
- Apply only approved changes to line quantities and promise dates. For each order, total the units accepted on or before each line's own promise date. A later line deadline does not extend an earlier one. Exclude rejected units and keep SKUs separate.
- Use the date the contract measures. If it measures receipt or acceptance, do not substitute dispatch dates.
- An order passes only when every applicable line is complete by its own promise date. A late top-up may close an order commercially but cannot change its historic on-time result.
- Divide passing orders by eligible orders, round half up to one decimal place and report the denominator. With no eligible orders there is no percentage. Keep the IDs that missed so the supplier can trace them.
What to have ready
If something’s missing, your agent asks before it starts.
- Order IDs, promised dates, required quantities and any approved changes.
- Dated accepted quantities, cancellation evidence and report cut-off.

How does the contract define on time and in full: by order or by line, against which date, measured on dispatch or on acceptance, and with any tolerance?

Which reporting period and cut-off date apply, and how are cancelled orders treated?

Can you provide the full register of orders due in the period, not only those delivered? Overdue orders that have not arrived still count.
Try it on your own AI
A new question with a known answer, so you can check your AI gets it right.
-
Copy the questionWhat is our delivery performance by 2026-01-20? Return only JSON following the skill’s test format. Only order K is due 2026-01-25 and has already shipped. Order M due Jan 15 was cancelled in full on Jan 9.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
An empty measurement cohort has no percentage.
{
"eligible_orders": 0,
"passed": 0,
"percent": null,
"missed": []
}
The check runs in your browser. Nothing you paste is sent anywhere.
-
Copy the questionCalculate this week’s order-level OTIF using all five entries in the due register. Return only JSON following the skill’s test format. All five promised by the reporting cutoff. A and B accepted complete on time; C accepted complete one day late; D overdue and undelivered; E cancelled by buyer before its due date and excluded under the agreed policy.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
The undelivered overdue order belongs in the denominator. Cancellation E is excluded by the agreed definition.
{
"eligible_orders": 4,
"passed": 2,
"percent": 50,
"missed": [
"C",
"D"
]
}
The check runs in your browser. Nothing you paste is sent anywhere.
-
Copy the questionMeasure October whole-order OTIF at close on October 31. Return only JSON following the skill’s test format. A has one line due Oct 31, accepted Oct 31, and a second line due Nov 3, still open. B has one line due Oct 28 and one due Oct 31, both accepted on their own due dates. C had one September line due Sep 29, missed, and another due Oct 20, accepted Oct 20. D due Sept 30 failed and closed in September. No cancellations.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
B and C enter October because their final promise is then. C’s earlier miss stands. A is pending until November and D belongs to September.
{
"eligible_orders": 2,
"passed": 1,
"percent": 50,
"missed": [
"C"
]
}
The check runs in your browser. Nothing you paste is sent anywhere.
Where the method comes from
Free to use and adapt with credit (CC BY 4.0).