You ask in plain words
With whatever notes or documents you already have.
After all these variations, what are the contract’s agreed value and end date now?
What is agreed as at 2026-07-31?
Your notes
Baseline £10,000 and 2026-08-10. Both parties must sign. C1 both signed, effective July 2: +£800 and +5 calendar days. Identical C1 copy enclosed. C2 supplier signature only: +£300 and -3 days. C3 both signed, effective Aug 1: -£100.
Your agent answers with a checked method
It runs 5 checks before it replies.
Your agentUsing this skill
At 31 July the agreed value is £10,800 and completion is 15 August 2026. C1 adds £800 and five days, and its duplicate counts once. C2 lacks the second signature. C3’s £100 reduction takes effect in August.
- A requested service change can affect timing without adding money.
- Repeated attachments to email threads are often copies of one signed notice.
- Adding a replacement fee on top of the amount it replaces.
- Applying a change from its signature date when it states a later effective date.
- Counting a change signed by one party when the procedure requires both.
Why that’s right. Only one copy of C1 has both approval and effect by the cut-off.
Is it the right skill?
What it’s for, and when another skill or a person is the better choice.
Use it when
- Someone needs the current agreed contract value or completion date after several variations or change notices.
- A change log mixes signed, unsigned, proposed and duplicate changes.
- An invoice needs checking against the charge agreed after changes.
Not the right skill when
- Deciding whether a public contract modification is permitted under the Procurement Act 2023, or whether a contract change notice had to be published first. Refer that to the buyer's commercial or legal team.
- Negotiating or valuing a proposed change. The skill records what has been agreed, not what should be.
The method it follows
7 steps, in order, every time.
- Start from the signed baseline: value, fee basis (a fixed sum or a rate per period), currency and completion date.
- Use the change procedure's approval rule. Fix an as-of date and a unique ID for each notice. Treat an identical repeated copy as one notice, and hold conflicting signed versions for verification.
- Sort notices by effective date and contractual sequence. A proposal, an unsigned request under a signed-change policy or a change effective after the as-of date cannot alter the current baseline.
- Apply exactly what each approved change says: an incremental delta, a replacement amount or a recurring rate from an effective date. A replacement supersedes the named earlier amount; keep its history and stop the old rate when the replacement takes effect. If same-date changes conflict, use contractual precedence or hold the disputed amount instead of deciding by ID.
- Record accepted zero-value time changes as well as fee changes. Reconcile the baseline plus approved changes to the new value and completion date, and show unresolved notices alongside.
- When checking an invoice, apply the changes effective in its billing period and compare on the same fee and period basis. Report billed minus agreed as a signed amount.
- For a public contract under the Procurement Act 2023 (most public buyers in England, Wales and Northern Ireland), flag any applied change that alters value or term without a recorded contract change notice, for the commercial lead to check. The Act generally requires the buyer to publish a notice before modifying a public contract unless an exemption applies.
What to have ready
If something’s missing, your agent asks before it starts.
- Baseline fee and completion date from the signed agreement.
- Change IDs, signatures, effective dates and signed fee/date adjustments.

What does the contract's change procedure require for a change to take effect, such as both signatures, a set form or an authorised signatory?

At what date should the position be stated?

Can you share every change notice in full, including duplicates, rather than a summary list? Copies and conflicting versions need comparing.
Try it on your own AI
A new question with a known answer, so you can check your AI gets it right.
-
Copy the questionUpdate the baseline using this change register. Return only JSON following the skill’s test format. At 2026-10-01, contract €3,000 due 2026-11-01. C8 signed by both and effective 2026-09-28: replace completion with 2026-11-06, no fee change. C9 two inconsistent signed copies effective Sep 29, one +€30 and one +€50.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
The date change is effective despite its zero value. The conflicting fee change needs its operative version.
{
"value": 3000,
"completion": "2026-11-06",
"applied": [
"C8"
],
"held": [
"C9"
]
}
The check runs in your browser. Nothing you paste is sent anywhere.
-
Copy the questionCheck the June recurring invoice and identify changes in force. Return only JSON following the skill’s test format. Baseline £1,000 per month, completion 2026-12-31. Both signatures required. C01 effective May 1 signed by both: add £200/month. C02 unsigned June proposal: from July replace the C01 uplift with £300/month total. June recurring invoice £1,500. As of June 30.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
June is £1,200, leaving £300 above the agreed charge. C02 is proposed, applies to a later period and describes a replacement.
{
"value": 1200,
"completion": "2026-12-31",
"applied": [
"C01"
],
"held": [
"C02"
],
"billed_less_agreed": 300
}
The check runs in your browser. Nothing you paste is sent anywhere.
-
Copy the questionWhat agreed monthly charge applies at the end of July? Return only JSON following the skill’s test format. Baseline £1,000/month, completion 2026-12-31. Both signatures required. C01 approved by both effective May 1 adds £200/month. C02 approved by both effective July 1 replaces the C01 uplift with £300/month. As of July 31.
-
Ask your AI in a new chat
Give it this skill first, then paste the question. It replies with a short block of data in the format the skill asks for.
-
Show the answer and why
The July replacement supersedes the £200 uplift. The audit trail retains both approved notices.
{
"value": 1300,
"completion": "2026-12-31",
"applied": [
"C01",
"C02"
],
"held": []
}
The check runs in your browser. Nothing you paste is sent anywhere.
Where the method comes from
Free to use and adapt with credit (CC BY 4.0).
Use this skill in Raq.com
Add it to your Skill Library and your agent applies it whenever a request matches. Edit it for your own business and keep every version.